Skip to content

Ticking off the checklist

A checklist is a list of tasks that should be done on a job, for example “Device switched off”, “Filter replaced”, “Tightness checked”. It is at the very top of the job, in the area of the collapsible sections. The office creates it. In the app, you tick off the items.

The office creates checklists on the web. It saves recurring lists as “Checklist templates” (in the settings) and applies them to a job with one click. It can mark individual items as required. In the app you cannot add, change or delete items. You can find more under Jobs in the office.

If a job has no checklist, the section does not appear.

  1. Open the job. The section “Checklist (x/y)” is open at the start. The brackets show how many items are already done, for example “Checklist (2/5)”.
  2. Tap an item to tick it off. A tick in a coloured circle means “done”, a cross in a grey circle means “open”.
  3. If you tapped by mistake, tap the item again. It is then open again.

When you tick an item, the server stores who ticked it and when. If you take the tick back, the server deletes both. Only the items that are currently ticked count.

A required item is recognisable by a red star after the text for as long as it is open. Required items block completion:

  • On the “Completion” page, the list of requirements contains “Required checklist complete”. As long as a required item is open, it is not met. A tap on this row takes you back to the job.
  • If you try to complete anyway, the server replies: “Can’t complete: the required checklist is still open.” In the job view it says “Required checklist is still open!”.
  • This applies to everyone, including team leads and the office, and also with “Force completion”. All other requirements (time, material, photo, signature) can be bypassed in exceptional cases, open required items cannot.

Items without a star are recommendations. They block nothing.

Item Appearance Effect on completion
Done Tick in a coloured circle none
Open, without star Cross in a grey circle none
Open, required Cross in a grey circle and red star blocks

If the job belongs to a colleague, you can see the ticks but not change them. A lock appears next to the heading.

  • Ticking needs a network, because every tap goes straight to the server. If it does not work, a message such as “Could not save.” appears, and the item stays as it was.
  • The checklist has no photos or notes per item. For evidence photos use Photos, for comments use “Office” (Messages).
  • Whoever ticked last counts. If two technicians tick the same item, the name of the one who tapped last is shown in the end.

Completion says “the required checklist is still open”, but I see no open item. Pull the job down to reload it. The office has probably added a required item in the meantime. Look for the red star.

Can I skip items? Only items without a star. Required items must be done, even if the customer does not want to sign or the team is already finished.

Who sees that I ticked an item? The office sees the status of the checklist in the job. The server records who ticked it.